Eaton required full DO-160 qualification for three revised fuel pumps to support aircraft certification, with schedule and compliance risk across multiple test regimes.
KDC acted as an embedded delivery partner, owning qualification planning, documentation and reporting under a fixed-price, task-driven engagement, with customer and OEM test and documentation review and feedback.
This approach provided regulatory assurance, protected the certification schedule and enabled confident progression to manufacturing and in-service support.

REQUIREMENT
Full qualification required for three new / revised fuel pumps to support aircraft certification
SKILLS & TOOLS
- Experience in RTCA DO-160 Environmental and Electro-Magnetic Compatibility (EMC) testing
- Authorised Boeing Test Witnesses
WAY OF WORKING
Contractual Terms
Fixed Price
Agile Sprint Tasking
SQEP Capability Provision
Engagement Model
Offsite, independent task execution
Task-driven SQEP Capability Provision
Resource deployed to customer team
TASKING
- Compile qualification requirements
- Write qualification test procedures
- Write qualification by similarity reports
- Support testing
- Write qualification test reports
DELIVERABLES
- Qualification by similarity reports x3
- Qualification Test Reports x3
OUTCOME
Test reports delivered to Eaton end customer for 3x fuel pumps over a 2-year program.