/ Aerospace A220 Test Rig Design, Commissioning and Operation
Aerospace

A220 Test Rig Design, Commissioning and Operation

KDC designed, commissioned and operated the Test Rig to complete endurance testing to ensure through life component reliability.

Ways of Working

Contractual Terms

Fixed Price

Agile Sprint Tasking

SQEP Capability Provision

Engagement Model

Offsite, independent task execution

Task-driven SQEP Capability Provision

Resource deployed to customer team

Airbus Canada required the design and commissioning of a dedicated endurance test rig to address in-service fuel system reliability concerns on the A220 programme, with stringent safety and validation requirements.
KDC is acting as an integrated delivery partner under a fixed-price, task-driven model, leading multi-disciplinary rig design, control system development, V&V and commissioning through to operational testing.
This established a controlled endurance test capability, reduced through-life risk, and provided validated evidence to support component life extension decisions.

Requirement

Airbus Canada approached KDC with a requirement to test a fuel system component to determine in service reliability concerns. This was an endurance test designed to validate the increase to the component life.

Skills & Tools 

  • Structural design and analysis, explosive atmosphere electrical system design, control system design, fluid mechanical and thermal design.
  • Creation of SOP, training manuals/plans and supervisory protocols. LabView, Python and TCL.

Tasking

Mechanical, fluid mechanical, electronics/electrical, rig management control system and GUI design. Commissioning of the entire test rig including full requirements V&V. Development of operating & training procedure and delivery of endurance testing.

Deliverables 

  • Design phase – final acceptance.
  • ATEX – final acceptance.
  • V&V report.
  • Commissioning report – final acceptance.
  • Rig operation as per SOPs by KDC SQEP.

Outcome

Endurance test has been in successful operation for 18 months. Testing 50% complete and on schedule to complete in 2027.

 

Share this case study

Ways of Working

Contractual Terms

Fixed Price

Agile Sprint Tasking

SQEP Capability Provision

Engagement Model

Offsite, independent task execution

Task-driven SQEP Capability Provision

Resource deployed to customer team

New Hydrogen Test Facility Development

Submarine Design Certification & Legislative Compliance

Lifting and Turning Structural Analysis