/ Aerospace Antenna Installation Design Support for H125 and H145 Aircraft
Aerospace

Antenna Installation Design Support for H125 and H145 Aircraft

Enabled airworthy antenna integration across H125 and H145 platforms.

Way of Working

Contractual Terms

Fixed Price

Agile Sprint Tasking

SQEP Capability Provision

Engagement Model

Offsite, independent task execution

Task-driven SQEP Capability Provision

Resource deployed to customer team

QinetiQ required antenna installation designs for Airbus H125 and H145 helicopters within a classified programme, with configuration, airworthiness and integration constraints across multiple aircraft variants.

KDC Projects operated as a fixed-price delivery partner, undertaking aircraft surveys, mechanical and electrical design, CAD modelling and drawing release through to installation trial support.

This provided assured installation definitions, reduced integration risk during modification, and enabled progression through review, test and flight clearance activities.

Requirement 

QinetiQ required installation designs for antennas on  Airbus H125 & H145 Helicopters for a classified project.

Skills & tools 

  • SolidWorks
  • AutoCAD
  • Aircraft surveys (3D scanning)

Tasking 

Investigation and design of mounted COTS parts inclusive of Mechanical and Electrical design. Drawings were checked and released by KDC internal checkers. KDC support provided through trial installation, including rapid prototyping of space models.

Deliverables 

  • Preliminary Design Review – Installation concept models (CAD) and prototype test fit.
  • Critical Design Review – installation drawing pack pre-release
  • Installation Drawings and CAD – delivered as finished.

Outcome 

KDC Projects delivered this Fixed Price Work Package to time, cost, and quality requirements. Onsite and remote installation support was provided flexibly to ensure smooth program delivery. KDC collaborated closely with QinetiQ throughout engaging in regular onsite reviews. Test flights were completed successfully enabling the next stage of the project.

Share this case study

Way of Working

Contractual Terms

Fixed Price

Agile Sprint Tasking

SQEP Capability Provision

Engagement Model

Offsite, independent task execution

Task-driven SQEP Capability Provision

Resource deployed to customer team

New Hydrogen Test Facility Development

Submarine Design Certification & Legislative Compliance

Lifting and Turning Structural Analysis